ACTIVITIES Early demolition package is complete. Bids were received for the renovation scope on October 14. Brandt Construction is finalizing review of bids and getting subcontracts in place. Scaffold
CONSTRUCTION ACTIVITIES LEARN MORE DEMOLITION ACTIVITIES Selective Demolition is currently underway. Contractors are in the process of removing the old systems, including flooring, ceilings, piping,
DESIGN ACTIVITIES Project details are being finalized, including selection of interior finishes, landscaping, and final selections of historic fixtures FINISH BOARD LINK SITE PLAN LINK