RENOVATING FORMER INDIANAPOLIS VA HOSPITAL
Progress


November Through December 2025
ACTIVITIES Slate roof replacement Dormer repairs Finalize interior demolition
Jan 61 min read


October 2025
ACTIVITIES Early demolition package is complete. Bids were received for the renovation scope on October 14. Brandt Construction is finalizing review of bids and getting subcontracts in place. Scaffolding is being installed around the front of the building to start the replacement of the slate roof.
Jan 61 min read


September 2025
CONSTRUCTION ACTIVITIES LEARN MORE DEMOLITION ACTIVITIES Selective Demolition is currently underway. Contractors are in the process of removing the old systems, including flooring, ceilings, piping, ductwork, conduit and lighting, to help clear the way for the new systems to be put in place. You can now see the exposed structure of the building. BIDDING ACTIVITY A pre-bid was held on September 30th for contractors to learn about the project and walk the building in prep
Jan 61 min read
August 2025
DESIGN ACTIVITIES Project details are being finalized, including selection of interior finishes, landscaping, and final selections of historic fixtures FINISH BOARD LINK SITE PLAN LINK HISTORIC FIXTURE SCOPE LINK Received initial approval of scope from State Historic Preservation Office for Building 1 renovation Design estimated to be complete by end of August/early September
Jan 61 min read
July 2025
CONSTRUCTION ACTIVITIES Selective demolition in Building 1 Deconstruction and inventory of front stair to prepare for reconstruction
Jan 61 min read
June 2025
DESIGN ACTIVITIES Finalizing site survey and evaluation of storm lines Finalizing architectural, interiors, and structural drawings to submit to State Historic Preservation Office Finalizing direction on mechanical, electrical, plumbing, and technology systems with utilities and contractors CONSTRUCTION ACTIVITIES Demolition is anticipated to start in the next 2 to 3 weeks
Jan 61 min read